Re: (PILE FOUNDATION)Construction Of Two Luxury Duplexes (ikota) by raymondFirstborn(m): 6:19pm On Oct 21, 2023 |
Final course of blockwork |
Re: (PILE FOUNDATION)Construction Of Two Luxury Duplexes (ikota) by raymondFirstborn(m): 6:20pm On Oct 21, 2023 |
. |
Re: (PILE FOUNDATION)Construction Of Two Luxury Duplexes (ikota) by raymondFirstborn(m): 6:21pm On Oct 21, 2023 |
. |
Re: (PILE FOUNDATION)Construction Of Two Luxury Duplexes (ikota) by raymondFirstborn(m): 3:20pm On Oct 23, 2023 |
Approach view 1 Like |
Re: (PILE FOUNDATION)Construction Of Two Luxury Duplexes (ikota) by raymondFirstborn(m): 3:21pm On Oct 23, 2023 |
. |
Re: (PILE FOUNDATION)Construction Of Two Luxury Duplexes (ikota) by raymondFirstborn(m): 9:49am On Oct 26, 2023 |
We have started work on the slab |
Re: (PILE FOUNDATION)Construction Of Two Luxury Duplexes (ikota) by raymondFirstborn(m): 9:52am On Oct 27, 2023 |
Woodwork for slab |
Re: (PILE FOUNDATION)Construction Of Two Luxury Duplexes (ikota) by raymondFirstborn(m): 9:53am On Oct 27, 2023 |
progress so far 1 Like |
Re: (PILE FOUNDATION)Construction Of Two Luxury Duplexes (ikota) by raymondFirstborn(m): 7:11pm On Nov 01, 2023 |
Pent floor slab work ongoing. |
Re: (PILE FOUNDATION)Construction Of Two Luxury Duplexes (ikota) by raymondFirstborn(m): 7:12pm On Nov 01, 2023 |
Side view. |
Re: (PILE FOUNDATION)Construction Of Two Luxury Duplexes (ikota) by raymondFirstborn(m): 7:13pm On Nov 01, 2023 |
Approach view |
Re: (PILE FOUNDATION)Construction Of Two Luxury Duplexes (ikota) by raymondFirstborn(m): 3:49pm On Nov 02, 2023 |
Staircase 1 Like |
Re: (PILE FOUNDATION)Construction Of Two Luxury Duplexes (ikota) by raymondFirstborn(m): 9:06am On Nov 04, 2023 |
Update on our pent floor slab. |
Re: (PILE FOUNDATION)Construction Of Two Luxury Duplexes (ikota) by raymondFirstborn(m): 4:16pm On Nov 09, 2023 |
Update on the approach view. |
Re: (PILE FOUNDATION)Construction Of Two Luxury Duplexes (ikota) by raymondFirstborn(m): 4:17pm On Nov 09, 2023 |
Side 1 Like |
Re: (PILE FOUNDATION)Construction Of Two Luxury Duplexes (ikota) by raymondFirstborn(m): 6:08pm On Nov 13, 2023 |
Pent floor Slab. 1 Like |
Re: (PILE FOUNDATION)Construction Of Two Luxury Duplexes (ikota) by raymondFirstborn(m): 10:16pm On Nov 18, 2023 |
Approach view of our twin units |
Re: (PILE FOUNDATION)Construction Of Two Luxury Duplexes (ikota) by raymondFirstborn(m): 8:56pm On Nov 24, 2023 |
Pent floor work ongoing. |
Re: (PILE FOUNDATION)Construction Of Two Luxury Duplexes (ikota) by raymondFirstborn(m): 5:31pm On Nov 25, 2023 |
Blockwork on pent floor almost done. |
Re: (PILE FOUNDATION)Construction Of Two Luxury Duplexes (ikota) by raymondFirstborn(m): 5:33pm On Nov 25, 2023 |
Spot our stairway |
Re: (PILE FOUNDATION)Construction Of Two Luxury Duplexes (ikota) by money121(m): 6:36pm On Nov 25, 2023 |
|
Re: (PILE FOUNDATION)Construction Of Two Luxury Duplexes (ikota) by raymondFirstborn(m): 11:01pm On Dec 06, 2023 |
Work progress. Final work on the facade |
Re: (PILE FOUNDATION)Construction Of Two Luxury Duplexes (ikota) by raymondFirstborn(m): 11:02pm On Dec 06, 2023 |
. |
Re: (PILE FOUNDATION)Construction Of Two Luxury Duplexes (ikota) by raymondFirstborn(m): 11:04pm On Dec 06, 2023 |
Still working on the suspended beams |
Re: (PILE FOUNDATION)Construction Of Two Luxury Duplexes (ikota) by raymondFirstborn(m): 10:18am On Dec 07, 2023 |
. |
Re: (PILE FOUNDATION)Construction Of Two Luxury Duplexes (ikota) by raymondFirstborn(m): 6:57pm On Dec 07, 2023 |
Approach view 1 Like |
Re: (PILE FOUNDATION)Construction Of Two Luxury Duplexes (ikota) by raymondFirstborn(m): 7:50pm On Dec 07, 2023 |
|
Re: (PILE FOUNDATION)Construction Of Two Luxury Duplexes (ikota) by raymondFirstborn(m): 5:32pm On Dec 25, 2023 |
Merry Christmas |
Re: (PILE FOUNDATION)Construction Of Two Luxury Duplexes (ikota) by raymondFirstborn(m): 10:55pm On Jan 13 |
Happy new year |
Re: (PILE FOUNDATION)Construction Of Two Luxury Duplexes (ikota) by raymondFirstborn(m): 1:14am On Jan 14 |
|
Re: (PILE FOUNDATION)Construction Of Two Luxury Duplexes (ikota) by raymondFirstborn(m): 9:34am On Jan 14 |
|
Re: (PILE FOUNDATION)Construction Of Two Luxury Duplexes (ikota) by peleson1: 8:29am On Jan 15 |
raymondFirstborn: 5bedroom duplex + pent
CONTRACTOR - SHELTERMONICS NIG LTD
DURATION - 10MONTHS.
BUDGET - N60M(CARCASS (2UNITS) LOCATION - IKOTA
Contact details - 09056082348(call & Whatsapp)
raymondfubara@gmail.com
60m for the two Houses? On how many plots of land pls |